This $450 million project was executed for CABGOC for their South Nemba A platform offshore Angola. The platform is located at a 386-foot water depth in Block “O” offshore Cabinda, Angola. The primary construction barge accommodated 360 POB and had an 800-ton crane. Onshore fabrication was performed in our New Iberia yard and consisted of fabrication of ICP spools, two 200 ton modules, vessels skids, deck extensions, stair towers, secondary steel components, and fabrication of pipe and cable supports.
The offshore work was performed under full SIMOPS and the scope included:
The total project took four years including a 22-month offshore campaign. During the offshore work a total of almost 20,000 separate lifts were made. The entire project utilized almost 3 million man-hours with 2.5 million man-hours expended on the offshore portion with no lost time accidents.